Chapter 91: Project and delivery management
Project management is planning and controlling work that has a defined end: a brand launch, an exhibition that opens on a fixed date. Delivery management applies the same skills to a product team’s steady stream of releases. Designers meet both whenever someone asks when the work will be done.
Waterfall and agile
A waterfall project runs as a single pass through distinct phases, each finished before the next begins: requirements, design, build, test, launch. The Association for Project Management (APM) calls this a linear life cycle. An iterative life cycle repeats phases before moving on.1 Agile methods are the best-known iterative approach (→ 66 Design in agile teams).
The waterfall is usually traced to a 1970 paper by Winston Royce. Royce drew the sequence of steps, then wrote that he believed in the concept but that this implementation “is risky and invites failure”.2 Testing came last, so it was the first time the system met real conditions, and a failure there meant redesign and overruns of up to 100 percent. His fixes included building a pilot version first and involving the customer throughout. The word “waterfall” doesn’t appear in the paper.
A fixed sequence fits work where late changes are expensive: a printed annual report, packaging going to a die-cutter. Iteration fits work where nobody knows the right answer until people use something, which describes most software. Many design projects mix the two: a rebrand can run research and concepts iteratively, then switch to a fixed sequence once the identity goes into production.
Scope, milestones and dependencies
Scope is everything the project will produce and the work needed to produce it.1 The usual tool for pinning it down is a work breakdown structure (WBS), which splits the total into smaller parts until each one can be estimated and assigned. For a website, design might break into templates, components and states. A written list of what is out of scope is as useful as the list of what is in. Scope creep is the continual extension of scope after the plan is agreed; pricing and contracts that handle it are in → 92 Consulting and freelance practice.
A milestone is a key event in the schedule, usually tied to acceptance of something: concepts approved, content signed off, site live.1 A dependency is a relationship between activities: a template can’t be built until its design is approved, and content can’t go into it until it’s built.
The Gantt chart shows work as bars against time. In 1917 the US Army’s Chief of Ordnance hired Henry Gantt to track munitions orders, and during 1918 his charts spread to arsenals, aircraft production and shipbuilding.3 In Poland, Karol Adamiecki drew comparable charts, which he called harmonograms, but they weren’t published when he made them.4

Wallace Clark, The Gantt Chart (1922). Public domain. Cornell University Library, via Internet Archive.
A Gantt chart shows when, but not what depends on what. The critical path method (CPM) adds that. James Kelley of Remington Rand and Morgan Walker of DuPont developed it, ran it on a UNIVAC I and presented it in 1959.5 The critical path is the longest chain of dependent activities, and its total sets the project’s length.1 Activities off it have float, time they can lose without moving the end date.
Risk
A risk is a situation or event that could affect whether a project meets its objectives.1 Most teams keep a risk register, a list of identified risks with their probability, impact, owner and planned response.1 There are four kinds of response: avoid the risk by changing the plan, reduce its probability or impact, transfer it to someone else (an insurer, or a supplier under contract), or accept it and hold a contingency of time or money.1
Design projects have familiar risks: the approver is unavailable, content arrives late, a typeface license doesn’t cover the use (→ 94 Intellectual property and licensing). The psychologist Gary Klein proposed the premortem for finding them early. The team imagines the project has already failed, and each person writes down why. People with doubts get permission to raise them while the plan can still change.6
Estimation
An estimate is a forecast of the time or cost of completing work.1 Early estimates tend to be wrong in one direction. Daniel Kahneman and Amos Tversky named the planning fallacy in 1979: people expect their own project to go to plan even when they know most similar projects ran late.7 In a 1994 study, psychology students predicted on average that their senior theses would take 33.9 days. They took 55.5, and fewer than a third finished by their own best estimate.7
Bent Flyvbjerg reports cost overruns on nine out of ten megaprojects.8 The Sydney Opera House, designed by the Danish architect Jørn Utzon, was first estimated at AUD 7 million and cost AUD 102 million by its completion in 1973.9 Flyvbjerg puts the overrun at 1,400 percent in real terms.8
Steve McConnell’s cone of uncertainty describes how accuracy improves. At the initial concept, an estimate can be off by a factor of four either way, and the range narrows only as decisions are made, designing the interface among them.10 A three-point estimate reflects that range by giving best-case, most likely and worst-case values instead of one number.1 Reference class forecasting, which Flyvbjerg developed from Kahneman and Tversky’s work, starts from what comparable past projects actually took.11 Agile teams often size work in story points, a relative unit for user stories (→ 80 The software development lifecycle), and forecast from the points they completed in past sprints.1
RACI
A RACI chart is a responsibility matrix, with tasks or decisions in rows, people or roles in columns, and a letter in each cell. Responsible means doing the work. Accountable means owning the result and signing it off. Consulted means asked for an opinion before the decision, and informed means told afterward.12 The rule that does the most good is one A per row.12 Design approvals stall when three stakeholders each think they have the final say on the homepage. Draw the chart at kickoff and agree it with the people on it (→ 90 Multidisciplinary teams).
See also
66 Design in agile teams · 80 The software development lifecycle · 90 Multidisciplinary teams · 92 Consulting and freelance practice · 93 Design leadership and operations · 3 Design processes
Sources
- Association for Project Management (n.d.). “Glossary.” apm.org.uk.
- Buehler, R., Griffin, D. and Ross, M. (1994). “Exploring the ‘Planning Fallacy’.” Journal of Personality and Social Psychology 67(3), 366–381.
- Clark, W. (1922). The Gantt Chart: A Working Tool of Management. Ronald Press.
- Cornell University IT (n.d.). “RACI and RASCI Definitions.”
- Flyvbjerg, B. (2006). “From Nobel Prize to Project Management: Getting Risks Right.” Project Management Journal 37(3).
- Flyvbjerg, B. (2014). “What You Should Know about Megaprojects and Why.” Project Management Journal 45(2).
- Guinness World Records (n.d.). “Largest proportional increase in cost for a building project.”
- Kelley, J. E. and Walker, M. R. (1959). “Critical-Path Planning and Scheduling.” Proceedings of the Eastern Joint Computer Conference.
- Klein, G. (2007). “Performing a Project Premortem.” Harvard Business Review.
- McConnell, S. (2008). “Software Development’s Cone of Uncertainty.” Construx.
- Royce, W. W. (1970). “Managing the Development of Large Software Systems.” Proceedings, IEEE WESCON.
- Sobolewska, O. and Waszkiewicz, M. (2017). “Prawa harmonii jako kanwa zwinnego zarządzania projektami w organizacjach sieciowych.” Zarządzanie. Teoria i Praktyka 20(2).
Notes
- Association for Project Management (n.d.). “Glossary,” entries for linear life cycle, iterative life cycle, scope, scope creep, breakdown structure, milestone, dependency, critical path, float, deliverable, risk, risk register, reduce, transfer, contingency, estimate, three-point estimate and story point. https://www.apm.org.uk/glossary ↩ ↩ ↩ ↩ ↩ ↩ ↩ ↩ ↩ ↩ ↩
- Royce, W. W. (1970). “Managing the Development of Large Software Systems.” Proceedings, IEEE WESCON, August 1970, 1–9. https://www.praxisframework.org/files/royce1970.pdf ↩
- Clark, W. (1922). The Gantt Chart: A Working Tool of Management. New York: Ronald Press, preface, iii–iv. https://archive.org/details/cu31924004570853 ↩
- Sobolewska, O. and Waszkiewicz, M. (2017). “Prawa harmonii jako kanwa zwinnego zarządzania projektami w organizacjach sieciowych.” Zarządzanie. Teoria i Praktyka 20(2), 31–37. https://bazhum.muzhp.pl/media/texts/zarzadzanie-teoria-i-praktyka/2017-numer-2-20/zarzadzanie_teoria_i_praktyka-r2017-t-n2_20-s31-37.pdf ↩
- Kelley, J. E. and Walker, M. R. (1959). “Critical-Path Planning and Scheduling.” Proceedings of the Eastern Joint Computer Conference, 160–173. Scan from the Computer History Museum collection. https://mosaicprojects.com.au/PDF/PM-History_Critical_Path_Planning_&_Scheduling_Kelley_and_Walker_1959.pdf ↩
- Klein, G. (2007). “Performing a Project Premortem.” Harvard Business Review, September 2007. https://hbr.org/2007/09/performing-a-project-premortem ↩
- Buehler, R., Griffin, D. and Ross, M. (1994). “Exploring the ‘Planning Fallacy’: Why People Underestimate Their Task Completion Times.” Journal of Personality and Social Psychology 67(3), 366–381, citing Kahneman and Tversky (1979), “Intuitive prediction: Biases and corrective procedures.” https://bear.warrington.ufl.edu/brenner/mar7588/Papers/buehler-et-al-1994.pdf ↩ ↩
- Flyvbjerg, B. (2014). “What You Should Know about Megaprojects and Why: An Overview.” Project Management Journal 45(2), 6–19. https://arxiv.org/abs/1409.0003 ↩ ↩
- Guinness World Records (n.d.). “Largest proportional increase in cost for a building project.” https://www.guinnessworldrecords.com/world-records/382062-largest-proportional-increase-in-cost-for-a-building-project ↩
- McConnell, S. (2008). “Software Development’s Cone of Uncertainty.” Construx white paper, adapted from Software Estimation: Demystifying the Black Art (2006). https://www.construx.com/wp-content/uploads/2019/02/CxWhitePaper_ConeOfUncertainty.pdf ↩
- Flyvbjerg, B. (2006). “From Nobel Prize to Project Management: Getting Risks Right.” Project Management Journal 37(3), 5–15. https://arxiv.org/abs/1302.3642 ↩
- Cornell University IT (n.d.). “RACI and RASCI Definitions.” https://it.cornell.edu/index.php/it-service-management/raci-and-rasci-definitions ↩ ↩